Non-Technical Survey (NTS), Technical Survey and Land Release

by DEMINETEC.

Non-technical survey (NTS) is the collection and analysis of data about explosive ordnance contamination without intrusive intervention: records, interviews, accident data, imagery and field visits. Together with technical survey (TS) and clearance, it forms land release, the process defined in IMAS 07.11 by which land is cancelled, reduced or cleared on the basis of evidence. In the DEMINETEC Group, the Ukrainian and Iraqi entities are certified or accredited for both survey steps, and GEODE trains national survey teams.

NTS, technical survey and clearance at a glance

StepWhat is doneResultIMAS
Non-technical survey (NTS)Collection and analysis of data without intrusive intervention: records, interviews, accident data, imagery, field visitsSuspected and confirmed hazardous areas defined; land with no evidence of contamination cancelled08.10
Technical survey (TS)Intrusive investigation with detectors, excavation, sampling lanes and, where appropriate, machinesPresence, type and limits of contamination confirmed; area needing full clearance reduced08.20
ClearanceRemoval or destruction of all specified explosive ordnance to a specified depthCleared land, documented and handed over09.10 and 09.11

The three steps are not always run one after the other. IMAS 07.11 allows land to be cancelled at any stage of the process, as soon as reliable information shows that there is no evidence of contamination.

What a non-technical survey collects

NTS answers one question before any team enters the ground: where is there evidence of explosive ordnance, and where is there none?

Records and archives

Military records, conflict history, former military sites and ammunition depots, accident and incident reports.

Interviews

Local populations, authorities, landowners and former combatants: where fighting took place, where items were seen, where accidents happened.

Imagery

Aerial and satellite imagery, used to locate craters, trenches, positions and changes in land use.

Field visits

Observation from safe ground, marking of the limits of suspected areas and recording of coordinates.

The survey defines suspected hazardous areas (SHA), where contamination is suspected on the basis of indirect evidence, and confirmed hazardous areas (CHA), where direct evidence exists. Land for which no evidence is found is cancelled and recorded as such in the national mine action database.

Technical survey: confirming and reducing

Technical survey starts where information alone can no longer decide. Teams enter the hazardous area with detectors, excavation tools, sampling lanes and, where the ground allows it, mechanical assets. They confirm the presence or absence of explosive ordnance, identify its type and fix the boundaries of the contamination.

The result is a smaller, better defined area for full clearance. In mined areas, that clearance is mine clearance; where the hazard is unexploded and abandoned ordnance, it is battle area clearance (BAC).

Land release: cancel, reduce, clear

IMAS 07.11 defines land release as the process of applying all reasonable effort to identify, define and remove all presence or suspicion of explosive ordnance through non-technical survey, technical survey and clearance. Land leaves the list of hazardous areas in one of three ways: it is cancelled when there is no evidence of contamination, reduced after technical survey, or cleared.

The purpose is practical. Clearing land that is not contaminated uses teams, time and funding that are needed elsewhere. A documented survey concentrates clearance on the areas that need it and gives the authority a traceable basis for returning the rest to its users.

Survey for infrastructure and energy projects

On construction and energy projects, the same logic applies under other names. A historical desk study gathers the evidence on the footprint and its access routes. A geophysical UXO survey then confirms and locates anomalies. Clearance is limited to the areas and depths that foundations, trenches and earthworks require, and a clearance certificate is issued per area and depth.

In countries with a national mine action authority, the survey methodology, the reporting format and the handover documents follow the national mine action standards. See UXO, ERW and mine action standards and regulation.

How the DEMINETEC Group delivers survey

DEMINETEC Ukraine

Non-technical and technical survey are among the five mine action processes for which the Ukrainian entity is certified to DSTU 8820:2023 (August 2025).

DEMINETEC Iraq

Non-technical and technical survey are among the eight activities covered by the accreditation licence issued by Iraq’s Directorate of Mine Action in October 2025.

GEODE

Survey methodologies and standard operating procedures, training of NTS and TS teams in Tajikistan, land release training of trainers in Benin. See GEODE’s non-technical and technical survey services.

DEMINETEC and UXOMAP

Historical desk studies and geophysical UXO surveys on land and, with SEMTEC, underwater, for developers, EPC contractors and energy companies.

Since 2023, the group has been pre-qualified by UNOPS in 14 disciplines for explosive threat mitigation services. Its international references cover 34 countries.

Applicable standards

StandardScope
IMAS 07.11Land release
IMAS 08.10Non-technical survey
IMAS 08.20Technical survey
IMAS 09.10Clearance requirements
IMAS 09.11Battle area clearance

The full texts are published on the International Mine Action Standards website. National mine action standards, based on IMAS, apply in each country.

Frequently asked questions about non-technical survey

What is a non-technical survey (NTS)?

A non-technical survey is the collection and analysis of data, without intrusive intervention, about the presence, type and distribution of explosive ordnance contamination. It relies on records, interviews, accident data, imagery and field visits, and is covered by IMAS 08.10.

What is the difference between non-technical survey and technical survey?

Non-technical survey works from information and observation, without physical intervention in the hazardous area. Technical survey is intrusive: detectors, excavation, sampling lanes or machines are used to confirm the presence or absence of explosive ordnance and to fix its boundaries.

What is land release?

Land release is the process of applying all reasonable effort to identify, define and remove all presence or suspicion of explosive ordnance through non-technical survey, technical survey and clearance (IMAS 07.11). Land is cancelled, reduced or cleared.

What do SHA and CHA mean?

A suspected hazardous area (SHA) is an area where contamination is suspected on the basis of indirect evidence. A confirmed hazardous area (CHA) is an area where the presence of contamination has been confirmed on the basis of direct evidence.

Does a non-technical survey replace clearance?

No. It decides where clearance is needed. Land with no evidence of contamination is cancelled; land where evidence exists goes to technical survey and clearance.

Who carries out non-technical survey in the DEMINETEC Group?

DEMINETEC Ukraine and DEMINETEC Iraq are certified or accredited for non-technical and technical survey in their countries. GEODE designs survey methodologies and trains national NTS and TS teams.